\documentstyle[a4,psfig,12pt]{article}
%\setlength{\textwidth}{6.375 true in}
\setlength{\textwidth}{6.000 true in}
\setlength{\textheight}{655 pt}
%\pagestyle{empty}
\renewcommand{\thefootnote}{\fnsymbol{footnote}}
\newcommand{\cc }{$^{12}$C}
\newcommand{\oo }{$^{16}$O}
\newcommand{\mg }{$^{24}$Mg}
\newcommand{\be }{$^{8}$Be}
\newcommand{\si }{$^{28}$Si}
\newcommand{\neon }{$^{20}$Ne}
\newcommand{\he }{$^{4}$He}
\newcommand{\al }{$\alpha $}
\newcommand{\gam }{$\gamma $--ray}
\newcommand{\degree }{$^\circ $}
\newcommand{\action }[1]{\hfill \fbox{#1}}
\begin{document}

\setlength{\unitlength}{1cm}
\noindent
\begin{picture}(0,0)
\put(0,2.5){\makebox(0,0)[l]{CH/Meet/93/04}}   %% Reference number of document
\end{picture}

\noindent
\begin{minipage}[t]{10cm}
\fbox{
\parbox[t]{5cm}{
{\large {\bf Minutes}}\\[2mm]
Charissa Group Meeting
}}\\[7mm]
\makebox[3.5cm][l]{Meeting held on:} 14 July 1993\\[2mm]            % Date
\makebox[3.5cm][l]{Meeting held at:} Oxford \\[2mm]     % Place
\end{minipage}
\hfill \raisebox{-2.5cm}{
\psfig{figure=char-encap.ps,height=3cm}}\\[2mm]

\begin{center} \begin{tabular}{l@{~~}l} \hline
~\\								% Present
\makebox[2.5cm][l]{Present:} & \parbox[t]{12cm}{
DLW(Chair),WNC,NMC,MF,GJG,RAH,CDJ,ACM,VP,WDMR,RPW\\
plus B. Brooks, D. Savory, S. Lawson, D. Smith, R. Wastie (present 
for Items 4, 5, 6, 7 and 8.)
}\\
~\\								% Apologies
\makebox[2.5cm][l]{Apologies:} & \parbox[t]{12cm}{
RAC,BRF,SJAH,JK,JSL,GT,JZ
}\\
~\\								% Distribution
\makebox[2.5cm][l]{Distribution:} & \parbox[t]{12cm}{
Those above plus  DDW, all by e-mail/file-server.
}\\
~\\ \hline
\end{tabular}
~\\[0.5cm]
%\addtolength{\headheight}{2.5cm}
{\large {\bf Minutes}} \\[0.5cm]

\begin{minipage}{12cm}
{\it The meeting was preceded by a short demonstration of electronics.
This included bias supplies in their rack, latest prototypes of
amplifiers and channel control units, and a module used for testing
the amplifiers.} \end{minipage}
 \end{center}


\begin{enumerate}
%\addtocounter{enumi}{-1}

\item	 {\bf Minutes of meeting of 13 May:} accepted

\item	 {\bf Matters Arising/ Actions:}
\begin{enumerate}

\begin{itemize}

\item	 {\it Item 4: Detector Tests} \\
	DLW reported that Hamamatsu and Intertechnique executives had
	recently met with him in York to discuss detector performance.
	S. Chappell would produce a drawing of a new PCB mount for Hamamatsu
	detectors by 1 September, which would be distributed. \action{DLW}

	S. Chappell would also produce a report on detector performances
	by mid-September, for distribution to all groups. \action{DLW}

	It was planned to ask for quotes before 30 September, receive them by
	30 November and place orders immediately for March 1994 delivery.

	NMC reported that drawings by N. Curtis were with the Birmingham
	workshop, and manufacture had begun, for a scintillator mounted
	behind the silicon in a hybrid detector.

\item	 {\it Item 5: New Array} \\
	DLW reported that work on the MEGHA prototype had restarted in York
	following completion of the ANU requirements.

\item	 {\it Item 6: Gas Supply}\\
	DLW reported that the mechanical construction was underway, and testing
	with air was anticipated  by 7 August.

\item	 {\it Item 9: ANU detectors} \\
	The final design for the modified hybrid mounts had been agreed and
	three completed mounts had been shipped to the ANU. Detectors could
	be mounted 0--75 cm from the target. The T--piece for hermetically
	sealed
	Sealectro feedthroughs, with 4 inch Dependex coupling, had been
	completed and shipped. Spare grids and windows had been sent; a list
	provided by RAC was circulated at the meeting. This list included a 
	series of detector tests recommended by RAC.

	The first shipment to the ANU had arrived satisfactorily on 6 July.
	The subsidiary air shipment was due to arrive on 19 July.

	It was agreed that the 
	hybrid tests recommended by RAC should be carried out
	by RPW, CDJ and SJAH using the first beam time 
	available at the ANU. \action{RPW,CDJ,SJAH}

	Reports from BRF had been received regarding progress by the team
	presently at the ANU. The setting up had advanced well, and cables
	were currently being laid.

	VP would be travelling to the ANU on 23 July, to stay 3 weeks and
	set up the data acquisition.	

\item	 {\it Item 10: Strasbourg} NMC reported that JSL had discussed 
	with Strasbourg the requirements for the Charissa beam line. It
	appeared that one quadrupole doublet was sufficient, and enquiries
	were being made regarding power supplies.

\item	 {\it Item 11: ANU timetable} \\
	Information on obtaining Australian visas had been distributed by
	RPW and was now on the server (CH/Doc/93/11).

\end{itemize}

\end{enumerate}


\item	 {\bf Update on NSC/SERC matters:} 

	DLW reported that the NP committee was likely to be in the 
	Engineering and Physical Sciences Research Council (EPSRC) when
	the new research council structure comes into force (April 1994).

	It was expected that the date for submission of new grant applications
	would be February 1994 or 15 March 1994.

\item	 {\bf Progress Reports on Electronics:} 

\begin{enumerate}

\item	 {\it Amplifiers and Channel Control Units}

Dick Hunt reported. The aims of the new design had been

\begin{enumerate}

\item	 Generate individual gating and walk times for each channel,
	allowing gated integrators to be used.
\item	 Provide remote control of amplifier gain, discriminator
	thresholds, pole zeros, walk duration (500--800 ns typical)
	and gate length (up to 15$\mu $s for integrator, down to 3$\mu $s
	for peak-sampling).
\item	 Include conversion of amplifier output to time duration.

\end{enumerate}

There were 32 completed amplifiers (prototypes).

For the production run of 320 units, the following changes are envisaged:
\begin{enumerate}

\item	 Move the integrator unit and/or Silena peak unit from the CCU
	to the back part of the amplifer, which will
\begin{enumerate}

\item	 keep the analog electronics completely separate from CCU,
\item	 make the backplane inter-connections easier and cheaper.

\end{enumerate}
\item	 Redesign the discriminator, as present components are obselete.

\end{enumerate}

The gated integrator and sample circuits will be tested at Oxford using
signals from Ge detectors.

{\it Time constants:} the requirements were discussed, viz. 0.75$\mu $s
for gated integrators (followed by $\sim 10\mu $s integrating gate) and
about 2$\mu $s for gas and strips. Final decisions would be required for:
\begin{enumerate}

\item	 which time constants to provide, and

\item	 what procedure to implement for changing time constants on amplifiers
	`in the field', where large numbers may be involved.

\end{enumerate}

Comments on time constants should be forwarded to RAH
before the next meeting. \action{ALL}

\item {\it Preamplifiers}

Barney Brooks reported. The assembly of components onto the backplate
of the array modules was demonstrated: a board with high voltage filters
plugs into three vacuum feedthroughs; the motherboard plugs into three
connectors on the filter boards; each motherboard holds 18 preamps
servicing three telescopes; a shielding-can encloses each motherboard;
an endcap on each can has 24 Sealectro slide-on connectors.

One motherboard has to be different --- with hole for beam exit.


The individual preamps are small and difficult to handle and hence
will be fabricated in group of 12 on a single PCB. They will be tested
in this form and the individual preamps will only be removed when required for
installation on the motherboard. 

It was recommended that preamps should be conformally coated in order to
avoid extreme touch-sensitivity. This may affect operation in gas.


\item {\it Bias Supplies}

David Smith reported. Each supply module contained 2 supplies, and they
were arranged with 8 modules (16 supplies) per rack. Polarity was
switchable; it is anticipated that the majority will be used on positive.

Each rack also includes a mains/power supply unit and a controller.

The controller module
in each rack could be switched to `local' or `remote' operation. In local
operation each supply is addressed in hex 0--F. In remote operation an
RS--485 serial link sends crate address, supply address and voltage demand.
The software exists for manual control but not yet for remote control.

The controller is still
in an early prototype stage and the PCB still needs to be laid out.
The software to provide external control of the supplies for
experimental use, including that required to provide compensation for
leakage current variation, still has to be written. It was suggested
that LAB-windows should be employed.


\end{enumerate}

\item {\bf Costings:}

\begin{enumerate}
\item {\it Amplifiers etc.:}
RAH reported, with reference to Ch/Doc/93/09 which had been circulated
previously. (It was noted that some copies of this document had \$ signs
instead of \pounds\ but all figures refer to \pounds\ prices.)

Some estimates were necessarily uncertain. These were mainly: the PCB layout
for the amplifiers, and the channel interfaces. The crate cost could drop
when the CCU/amplifier rear cabling is modified. The integrator price could
rise after prototyping; the Silena unit appeared quite expensive.

\item {\it Preamplifiers:}
Barney Brooks reported. For 360 preamps the estimates were \pounds 10 for
components and \pounds 4 for assembly, plus VAT, per unit. The interconnecting
voltage filters were estimated at \pounds 45 each (60 off), mostly due to
HV capacitors. The motherboards were \pounds 22 each (60 off).

The endcaps for the cans have 24 Sealectro connectors.
DLW reported that \pounds 6 per connector was anticipated, giving
\pounds 150 per endcap (60 off).

\item {\it Bias Supplies:}
David Smith reported, with reference to Ch/Doc/93/10 which had been circulated
previously. Quotes had been obtained from Beorn, a local firm. It was agreed
that the best option was to build 70 modules with crates, to take advantage
of quantity savings.

\item {\it Data Acquisition:}
RAH confirmed that sufficient units for 256 channels had been purchased
last year. WDMR estimated that an extra \pounds 64K would be required to
achieve 320 channels and instrument the full array.
\end{enumerate}

{\it Summary:} all the estimates inclusive of VAT were collated:\\[1mm]
%\begin{figure}[ht]
%\caption{Cost Estimates for New Electronics}
\begin{center}
\begin{tabular}{|l|r|}
\hline
Category	      & \pounds \\ \hline
Amplifiers/CCU's etc. & 200K      \\
Bias supplies	      &  20K	  \\
Preamplifiers	      &  20K	\\
Data acquisition      &  64K	\\ \hline
TOTAL		      & 300K	\\
\hline
\end{tabular}
\end{center}
%\end{figure}\\[1mm]
DLW agreed to check these figures against those in the Grants. \action{DLW}

\item {\bf Division of Finance and Final Assembly/Testing:}

DLW summarised the situation: at the time of the Grant proposals, it had
been anticipated that Oxford would provide design and manufacturing effort,
and York extra manufacturing effort. These plans needed revision following
workshop restructuring pursuant to changes in methods of research funding.
BB pointed out that, further to this, Dennis Savory (Oxford) would be
retiring in July 1994.

WDMR undertook that design would be completed at Oxford for all components.

It was agreed that the meeting would address the division of responsibilities
for ordering, construction and testing:

\begin{enumerate}
\item {\it Amplifiers:} It was agreed that these would be the responsibility
of Oxford. Bulk orders would be placed with an external manufacturer,
and depending on funds these could
be placed jointly through different universities.

Testing of amplifiers and channel control units would be split between
Birmingham and Surrey primarily. Each of Birmingham, Surrey, York and Oxford
would require a CAMAC system for testing, to which they could connect
using an IBM PC. Testing would use the test module demonstrated before the
meeting, with problem units being referred back to Oxford. RAH noted that
there were CAMAC crates at Oxford, owned by Charissa, which could be 
utilised for testing at other sites.

\item {\it Preamplifiers:}
It was agreed that Oxford would produce a working prototype with 18
preamps. They are having 20 preamps built, as suggested by BB.
These will then be put in a single
can.  The main idea is to check there are no layout mistakes etc.\ on the
PCB. When the prototype is working satisfactorily, York will take over
responsibility for the preamps.

%It was agreed that final prototyping would be completed at Oxford.
%The required tests for the completed assemblies were outlined by BB and
%discussed. It was agreed that York would liaise with Oxford and
%would be responsible for placing orders. Daresbury would be considered as
%a possible manufacturer. BB recommended that
%a small batch, say 20, could be made commercially
%in the first instance, prior to a bulk order.
%
\item {\it Bias Supplies:}
It was agreed that when a working prototype had been produced at
Oxford then York would take over the responsibility for the manufacture
(either in-house or contracted out) and testing. The York group would
also look after the programme  to control the supplies from an external
computer.

%It was agreed that final prototyping would be completed at Oxford.
%Manufacture (either in-house or contracted out) and testing would be the
%responsibility of York.

\end{enumerate}

\item {\bf Timescales for Completion:}

	It was agreed to use March 1994 as the target date for one
	complete working module.

	DLW stated that the hardware construction would be completed by then.

	It was agreed to get preamplifiers for one module prepared in
	time, taking into account BB's suggestion under the previous Item
	that a trial batch be produced.

	RAH stated that prototype amplifiers could well be ready in time,
	but commercially produced units would not be available. WDMR proposed
	that it would be sensible to buy in effort to design the final PCB
	layout, rather than Oxford doing the artwork. It was agreed that
	RAH should pursue this by obtaining quotes from Beorn and one other
	company, on the basis of the final specification. \action{RAH}

	RAH stated that the prototyping of CCU's could possibly be complete
	by December 1993. However, commercial CCU's would probably not be ready
	for April testing.

\item	 {\bf Data Acquisition --- Preliminary Discussion:}

	WDMR introduced this topic: the aims were to partition responsibilities.

	It was agreed that the CAMAC would be done by Oxford. \action{RAH}

	The VME was agreed to be done by Oxford, Birmingham (SJAH) and 
	VP. \\ \mbox{} \action{RAH,SJAH,VP}

	The trigger logic responsibility (handling of coincidences and 
	multiplicities) was accepted by MF. \action{MF}

	The software would be coordinated by VP. He would liaise with all
	four universities. The areas identified for attention 
	were: \action{VP}

\begin{enumerate}
	\item 
fast on-line code in CAMAC to assemble data packages and send down FERA
	\item 
code in VME to handle the above
	\item 
control of the setup of CAMAC outstations using serial links
	\item 
control of channel interfaces
	\item 
control of bias supplies: code inside crates
	\item 
control of bias supplies: code in controlling computer
	\item 
changes to on-line and off-line sort programmes to handle possible new
formats
\end{enumerate}

	The code for the bias supplies had been dealt with by P. Simmons
so far; York would complete this, along with the hardware. \action{DLW}

The fast readout via FERA to VME was raised by VP. It transpired that
Oxford had passed the specification to Golding and the code was expected for
August. Thus, it would not be ready for running in September 1993. In the
first stage, the header formats would not be changed.

\item	 {\bf Any Other Business:}


\begin{enumerate}

\item	Any people anticipating language difficulties in Australia
	were recommended to read ``Aussie English'' by J. O'Grady,
	ISBN 0 7018 1585x.

\item	DLW raised the issue of detector stocks, with reference to the
	requirements for September running at the ANU. BRF had ascertained
	that present stocks were just sufficient. Reservations were
	expressed at the meeting, and it was generally agreed that the
	purchase of a small number of additional detectors would be
	appropriate. \action{DLW}

\item	Proposals for future runs at the ANU should be communicated to
	BRF. DLW anticipated a big demand on available beam time in order
	to satisfy committments to students at each university. He considered
	that the four days currently suggested for York experiments in
	April may not be sufficient. WNC agreed that demand for beam time
	was strong, noting that Surrey would certainly require one run
	in April.

\item	Offers to use the facilities of other laboratories had been received.
	DLW reported that Saclay had indicated an interest in housing an
	array for Charissa experiments. NMC reported that the Indra group
	were interested in collaboration at GANIL, and WNC reported other
	interest from researchers at GANIL. These possibilities would be
	explored.

\item	VP reported that additional memory was to be supplied to the
	workstations being installed at the ANU. These machines were 
	running the Solaris 2.2 operating system. It was anticipated to
	change UK machines over to Solaris 2.2 at the end of 1993.


\end{enumerate}

\item	 {\bf Date of Next Meetings:} \\


	Next Meeting: 1.15 p.m., Thursday, 9 September 1993 in York.\\

	(To be preceded by a sub-meeting at 11.00 a.m. and a
	display of new modules during the morning.)


\end{enumerate}


\mbox{}\\
W.N. Catford, Secretary.\\
July 27, 1993\\[1mm]
(released \today )

\end{document}















