\documentstyle[a4,psfig,12pt]{article}
%\setlength{\textwidth}{6.375 true in}
\setlength{\textwidth}{6.000 true in}
\setlength{\textheight}{655 pt}
%\pagestyle{empty}
\renewcommand{\thefootnote}{\fnsymbol{footnote}}
\newcommand{\cc }{$^{12}$C}
\newcommand{\oo }{$^{16}$O}
\newcommand{\mg }{$^{24}$Mg}
\newcommand{\be }{$^{8}$Be}
\newcommand{\si }{$^{28}$Si}
\newcommand{\neon }{$^{20}$Ne}
\newcommand{\he }{$^{4}$He}
\newcommand{\al }{$\alpha $}
\newcommand{\gam }{$\gamma $--ray}
\newcommand{\degree }{$^\circ $}
\newcommand{\action }[1]{\hfill \fbox{#1}}
\begin{document}

\setlength{\unitlength}{1cm}
\noindent
\begin{picture}(0,0)
\put(0,2.5){\makebox(0,0)[l]{CH/Meet/93/02}}   %% Reference number of document
\end{picture}

\noindent
\begin{minipage}[t]{10cm}
\fbox{
\parbox[t]{5cm}{
{\large {\bf Minutes}}\\[2mm]
Charissa Group Meeting
}}\\[7mm]
\makebox[3.5cm][l]{Meeting held on:} 7 April 1993\\[2mm]            % Date
\makebox[3.5cm][l]{Meeting held at:} Daresbury \\[2mm]     % Place
\end{minipage}
\hfill \raisebox{-2.5cm}{
\psfig{figure=char-encap.ps,height=3cm}}\\[2mm]

\begin{center} \begin{tabular}{l@{~~}l} \hline
~\\								% Present
\makebox[2.5cm][l]{Present:} & \parbox[t]{12cm}{
BRF(Chair),WNC,GJG,SJAH,RAH,JK,\\JSL,ACM,VP,WDMR,RPW,DLW
}\\
~\\								% Apologies
\makebox[2.5cm][l]{Apologies:} & \parbox[t]{12cm}{
NMC,RAC,CDJ,GT,JZ
}\\
~\\								% Distribution
\makebox[2.5cm][l]{Distribution:} & \parbox[t]{12cm}{
Those above plus  DDW, all by e-mail/file-server.
}\\
~\\ \hline
\end{tabular}
~\\[0.5cm]
%\addtolength{\headheight}{2.5cm}
{\large {\bf Minutes}} \\[0.5cm]
 \end{center}


\begin{enumerate}
%\addtocounter{enumi}{-1}


\item	 {\bf Minutes of Meeting of 10 February 1993:} accepted

\item	 {\bf Matters Arising:}

	JK requested that he and D.Warner be added to the distribution
	list of the Charissa  minutes. JK stayed at the present 
	meeting for Items 1,2,5,6 and 9.

	BRF reported that {\it Charissa labels} for electronics modules
	would be arranged and afixed upon unpacking in Australia. \action{SJAH}

\item	 {\bf Update on NSC/SERC matters:}

	{\it Present funding situation:} there was still no decision on
	the ABRC flexibility funds required to fund nuclear physics from
	1996/97. The government's White Paper was awaited.

	{\it RAL Test Bed:} this funding had not yet been authorised by SERC.\\
	\mbox{} [N.B. This authorisation has occurred since the Meeting.]

	{\it Following the closure of the NSF:} the disposal of minor
	equipment from DL would be reviewed again by DL staff and
	spokespersons for the NSC programmes. All equipment would be
	issued {\it on loan} and could be requested by other groups.

	The next meeting of the joint French/UK management committee
	dealing with {\it Eurogam} would also include Charged Particle
	representatives.

	The support group at DL was likely to be very heavily loaded with
	design and drafting requests,
	and effort must be planned well in advance.
	This was discussed, and it was agreed that outline plans for the
	new scattering chamber were required by September 1993.
	(See also, Item 5.) \action{JSL,DLW,JK}

	The support group staff will be funded through DL for travel in
	support of core activities, but meetings to discuss possible {\it future
	developments} may require funding from University rolling grant
	equipment lines.

	{\it Future SERC committee structure:} the NSC will be superceded
	by the Nuclear Physics Committee (NPC) of the new board for Particles,
	Astronomy and Space.

	A Charged Particle User Group is formally required by the NPC. It
	was agreed by the meeting that its present membership provided
	suitable representation of these interests.

	{\it Allocation of Beamtime at the ANU:}

	A joint NPC/ANU panel will approve programmes proposed for the ANU.
	Proposals will be submitted at any time, and the physics case and
	feasibility will be considered. Recommendations will be passed to
	the NPC, whose approval will be valid for 18 months. For running in
	April and September 1994, this implies submissions in August 93
	and February 1994 in practice. Scheduling of beamtime will be done
	by the ANU, who require at least 12 weeks' notice.

	A Charissa programme proposal is required before August. \action{BRF}

	{\it Funding of Travel to ANU Experiments:}

	Travel costs for Staff will need to be justified and supported,
	and charged against the grant. It was planned to continue supporting
	travel to the ANU via the university grants.

	Students will be funded through the Studentship office, who will
	decide what fraction of the requested costs they will award.
	Bids are made in advance and payment is retrospective (to a UK
	bank account) on production of supporting documentation and receipts.
	Each group should note that SERC-provided insurance for students
	will cover medical and baggage insurance, but death and disability
	insurance must be provided by other means.

	Regarding student funding, the meeting was concerned at the variations
	between the treatment of similar claims. It was agreed that BRF
	should prepare wording for bids to cover AM and ML, who are expected
	to be travelling out first. \action{BRF}

	{\it Annual Review of Programs:}

	It was noted that the NPC will require a review of the current Charissa
	programme at its meeting in September 1993, where it will grade
	the various programmes.
	It was expected that this
	would comprise a 30 minute presentation, supported by a short written
	summary and statistical details submitted in advance. It was thought
	that the review would concentrate on scientific development and would
	be required to highlight successes and problems. It should also
	address the continued participation of groups, the financial statements
	and planned expenditure, use of DL minor and major equipment,
	requests for same by other groups, administrative concerns, and a
	statement of DL and university manpower.

	It was agreed that each staff member should provide input to BRF
	towards the preparation of the review. \action{WNC,NMC,JSL,WDMR,DLW}

	It was further agreed that a meeting should be held to help prepare
	for the review, with a representative from each
	university. \action{BRF}

\item	 {\it Progress on Detector Tests:}

	DLW reported results obtained by Steve Chappell from beam tests
	of detectors under assessment:
	\begin{enumerate}

      \item    {\it Sheet resistance 2--D PSD's}

		Two detectors were tested with position signals taken from
		each corner through 510$\Omega $ resistors, and an energy
		signal taken from the back. The beam was carbon on a gold
		target, with detectors near 20 degrees (lab). A new calibration
		grid was employed, with wires of 0.5, 0.3, 0.2 and 0.1 mm
		diameter.
	       \begin{enumerate}
      \item    {\it Intertechnique} supplied a detector as used by the
		MULTICS collaboration. This displayed the familiar pin cushion
		effect. A simple 1--D projection of uncorrected data
		showed the 0.2 mm wires.
      \item    {\it Hamamatsu} supplied (for \pounds 3K) a detector with a
		lower-resistance on the perimeter of the resistive surface.
		A pepperpot mask gave an undistorted spectrum on-line.
		The wire grid gave uncorrected 1--D projections in which
		the 0.1 mm wires were very clearly seen.

		The energy signal depends strongly on position for short
		time constants (20\% dip at centre for 1$\mu $s, $\approx $0\%
		dip for 10$\mu $s). There was more data to be analysed
		for intermediate time constants.

		A single hole in the pepperpot gave 230~keV resolution for
		85~MeV $^{12}$C ions scattered from 100 $\mu $g~cm$^{-2}$ gold.


	       \end{enumerate}

      \item    {\it Strip Detectors}

		Detectors supplied by {\it Hamamatsu}  appeared to give
		energy and position resolution as good or better than
		{\it Micron} detectors, at 30\% less cost.

		The Hamamatsu  detectors also appeared to be much less prone
		to deterioration in-beam. The leakage was constant at
		$\sim 1 \mu $A while a Micron detector suffered an increase
		from 1 to 40 $\mu $A.

	\end{enumerate}

	A full report and decision regarding purchase of the 2--D detectors
	for the new array should be completed by September.

\newpage
\item	 {\bf Progress on Chamber and Detector Assemblies:}

	JK reported that prototypes were under construction at York.
	A vessel for nine telescopes was completed, and the backplate nearly
	completed. After discussions with NMC, the retaining clamp for the
	scintillators had been altered to be Tufnol and the springs would
	have extra tension. The {\it Verelec} vacuum feedthroughs were due at
	the end of April. Preamp can drawings had been issued to York and
	Oxford for information on 6 April. GA's for the nine-telescope
	module and beam-line layout would still require significant work.

	Anode and electrode drawings were with RAC for final
	comment. \action{RAC}

	NMC had requested a second scintillator mount. \action{DLW}

	It was agreed that JK should order parts required for prototype
	construction through York. \action{JK,DLW}

	{\it Timescales:} it was agreed that a module should be ready for tests
	at the ANU in March 1994. Availability for testing in September 1993
	was attractive, but not essential. A {\it full assembly} should be
	ready in time for running in September 1994. These timescales were
	considered to be realistic.

	{\it Priorities:} The following were agreed during the 
	meeting, under the indicated Agenda items: \action{JK}


\begin{table}[h]
\caption{Priorities for Workshop Jobs}
\begin{center}
\begin{tabular}{|l|l|c|}
\hline
Date Required & Description of Job 	&  Agenda \\ \hline
Immediate	& Modified detector arm plates  & 9 \\
~		& Flange adaptor		& 10 \\
~		& Other jobs for next run (Sep 93)	& ~ \\
August 93	& Possible mods to arm plates	& 9 \\
September 93	& Outline plans for new chamber	& 3 \\
Mar 94 at ANU 	& Nine-telescope module		& 5 \\
Sep 94 at ANU	& New gas handling system	& 6 \\
Sep 94 at ANU	& Full MEGHA assembly for running	& 5 \\
\hline
\end{tabular}
\end{center}
\end{table}


\item	 {\bf Progress on Gas Supply:}

	Design details had been agreed at the most recent MEGHA meeting
	and construction was proceeding at York.

	JK requested clarification of timescales. The new system was required
	for operation at the ANU in September 1994. (cf. Item 5, above.)

	RAC and JK would visit York to assess progress, which was believed
	to be good. \action{RAC,JK}

\item	 {\bf Progress on Electronics and Data Acquisition:}

	{\it Preamplifiers and Bias Supplies; Oxford Manpower:}

	WDMR reported that the design was essentially complete.

	The Department at Oxford had now implemented fully the system where
	technical staff are supported by grants. Charissa has effort from
	RAH ($\times 1.0$) and Dennis Savory ($\times 0.5$). It is certain
	that the manufacture of preamplifiers and biases will need to be
	contracted out. WDMR also stressed that tests on the completed items,
	and organization of these tests, would require help from outside
	Oxford. York was mentioned as a possible contributor.

	{\it Modifications to Event Manager EM4:}

	P. Simmons discussed this, with reference to document Ch/Tech/93/06.
	The aim was to modify the CAMAC to VME transfer, in order to release VME
	processor power for sorting and speed the transfer.

	In the present system, there is a serial link from the Read-and-Store
	module, via the Crate Controller, to the GEC emulator in VME.
	The serial CAMAC to VME transfer is 20 times slower than the HSM
	transfer rate.

	In the new system, a Starburst in CAMAC would respond to a LAM raised
	by the Event Control Module: it would read the header and the
	appropriate CAMAC parameters (TDC's, etc.) and write them to the
     base of the Data Stack (ADCs already written directly to stack by 
        FERA transfer).
        The existing CAMAC data stack (256 words capacity) would
        then output the completed event via FERA to an HSM unit in VME.

	The new system involves changing the header format for events.
	The implications for the on-line sorting program need to be
	investigated and the necessary modifications made. \action{VP}

	P. Simmons will write the necessary Starburst code in BASIC,
	and first tests will use this. RAH estimated that the modifications
	to the ECM unit would take 2 weeks.

	An assembler version of the BASIC code was needed for data
	acquisition. (In assembler, a CAMAC read is 100 times faster.)
	BRF expressed concern at the drain on manpower that this task
	could involve. After discussion, it was agreed that a contractor
	familiar with the system should be asked to tender.
	RAH agreed to approach Golding. \action{RAH}

	{\it Charissa Amplifier Development:}

        RAH reported, with reference to CH/Tech/93/05.

        Each amplifier has a Channel Control Unit that can remotely trim the
        fine gain, pole zero, and discriminator level. All settings are
        still available at front panel.

        Regarding the charge-to-time conversion, three prototypes are
        presently being assessed at Oxford, particularly with regard to
        linearity and the performance of surface-mount chips. These tests
        will be followed by tests for gain drifts etc.\ with
        gamma sources,  by P. Simmons.

        Construction is virtually complete at Oxford of 32 new amplifiers 
	that have been packaged into half-width modules.
	Construction of 32 prototype channel controls is also proceeding.
        The amplifiers that will be used in September at the ANU
        will be modified at ANU after the experiment.

        New amplifiers (256 in addition to above) are planned using 
	surface-mounted
        components. To go with these, 256 channel controls are also planned.
	Costings should be obtained before the July
        Charissa meeting. \\
        Daresbury should be asked to tender for
        surface-mounted manufacture if possible. \action{WDMR,RAH}


        Oxford should liaise with York electronics regarding the
        assembly and testing
        of the new amplifiers  -- the
        tests will need to be quite sophisticated. DLW reported that
        one person equivalent could possibly be provided. \action{RAH}

        Oxford and York should liaise with Daresbury regarding a possible
        contribution by DL to the amplifier assembly. \action{WDMR,DLW}


\item	 {\bf Developments on Event Manager and GEC Emulator:}

% From Vic:
%
% I would like to try and drop the phase GEC emulator if possible.
% It could be referred to as 
%   the data acquisition processor
%   the MVME187
%   the 88K system
%
%

	VP noted that the last two scheduled NSF experiments by Charissa
	had used the new Emulator 
        \footnote{VP recommends that the phrase ``GEC emulator''  be replaced
        by ``MVME187'' or ``data acquisition processor''}
	system for data acquisition. This had been
	successful.

	There had been some inconvenience due to the transfer of data from
	the event manager to VME, which slowed 
	down the on-line sorting but had been anticipated.
	The discussion under the previous Agenda item included
	the most recent work to modify the current Event Manager.

	VP reported that
	Hytec have delivered the unit ordered by Charissa for the VME/CAMAC
	interface, and the EPROM to repair problems in the first one.

	The coding for set up and reading of the HSM module in VME is
	underway at DL. A copy has been given to SJAH.

\item	 {\bf Requirements for Hybrid Detector Operation at the ANU:}

	BRF reported that the Planning Trip to ANU had identified the need
	for a revised method of detector mounting. It was suggested that an
	existing DL arm plate would be mounted upside down, with the
	hybrids suspended. S.Metcalf would work on this, and the scheme
	would be discussed at a meeting on 30 April.

	The new mounting plate was required at ANU for tests in July.
	Any significant modifications could be made in August, in the UK
	if required. \action{JK}

	This modified mount has the highest priority
	(see Item 5).

	The gas handling for the forthcoming September run will use the
	system already in place at the ANU (where propane is now used).

\newpage
\item	 {\bf Report on Planning Trip to the ANU:}

	BRF presented a document summarising the actions arising from
	the planning trip to ANU by BRF and JSL, in the previous week.
	\footnote{This handwritten document was
	circulated at the meeting, and has been
	allocated the number Ch/Doc/93/04, `Charissa at ANU'.
	More details may be found there.}

	{\it Unpacking of Container:} we are grateful that David Weisser
	has agreed to oversee arrival and unpacking of the container.

	{\it Office Space:} an office with space for 3--4 will be provided.

	{\it Visa Applications:} BRF will circulate application forms and
	a letter from ANU. \action{BRF}

	{\it Local Equipment and Incidental Expenses:} a \$10K fund would
	be set up at ANU via Birmingham. Charges to this fund will be
	authorised by G. Dracoulis via Paddy Regan.
	This fund will allow, e.g., materials from Stores
	and work by School Electronics to be paid for.
	(\$10K $\approx $ \pounds 5K).

	{\it Magnesium Beam Tests:} a 170 MeV $^{24}$Mg beam would be
	tested at ANU within the next 6 weeks, and we would be advised
	of the results.

	{\it Scattering Chamber Details:} The `Charissa at ANU' document
	Ch/Doc/93/04
	contains a list of 21 points concerning chamber and cable installation,
	including the following.

	The arm readouts were limited
	to 0.1 degree accuracy, and ANU are pursuing increased accuracy.
	The decision at the previous Charissa meeting, to buy extra
	carriages for inside the chamber, was revoked because their fitting
	would not be easy to achieve.

	It is required that the shielding on the signal cables be isolated
	from the chamber, so the details of the feedthroughs on the
	Daresbury chamber should be checked. An adaptor from the existing
	Charissa flanges to 4-inch Dependex (used at ANU) must be
	made. This is a top priority. \action{DLW,JK}

	Details of the proposed arrangement of cable racks, preamps and
	gas control around the chamber are included in Ch/Doc/93/04.

	{\it Targets:} can be made at ANU. Standard carbon and gold thicknesses,
	and flash gold have been requested already.

\newpage
\item	 {\bf Timetabling of Manpower for the ANU Experiment:}

	The proposals tabled by BRF in the previous Item involved three
	phases in the running of the experiment:

	{\it Installation Phase:} install chamber mounts and feedthroughs,
	main cable run, control room racks, electronics and DA computers.

	{\it Commissioning Phase:} commission electronics and DA system,
	including two test runs with beam.

	{\it Running Phase:} two periods of running, 27 Sep -- 4 Oct as
	two 4--day runs, 7--day break, then 11 -- 26 Oct as three
	4--day runs followed by clearup of chamber and electronics.

	The suggested timings, after discussions with the ANU, are
	given in Table 2.

\begin{table}[h]
\caption{Suggested Manpower for Next Run}
\begin{center}
\begin{tabular}{|l||c|c@{$\rightarrow $}c|ll|}
\hline
Phase	& Duration & From & Until & Core & Other \\ \hline
~	& ~	   & \multicolumn{2}{c|}{~} & ~ & ~ \\
Installation & 6 weeks & 5/7 & 13/8 & SJAH & BRF,GT,AM,ML \\
~	& ~	   & \multicolumn{2}{c|}{~} & ~ & ~ \\
Commissioning & 4 weeks & 30/8 & 24/9 & SJAH,RPW, & ~ \\
~	& ~	   & \multicolumn{2}{c|}{~} & CDJ & ~ \\
~	& ~	   & \multicolumn{2}{c|}{~} & ~ & ~ \\
Running & 5 weeks & 27/9 & 29/10 & SJAH,RPW, & NMC,WNC,GJG, \\
~	& ~	   & \multicolumn{2}{c|}{~} & CDJ & JP,NC,SS \\
~	& ~	   & \multicolumn{2}{c|}{~} & ~ & followed by \\
~	& ~	   & \multicolumn{2}{c|}{~} & ~ & WDMR,DLW,MF, \\
~	& ~	   & \multicolumn{2}{c|}{~} & ~ & PS,SF,SC \\
~	& ~	   & \multicolumn{2}{c|}{~} & ~ & ~ \\ \hline
\end{tabular}
\end{center}
\end{table}

	Generally, these were endorsed by the meeting. WDMR indicated that
	there should be some overlap in time between the two different groups
	covering the running phase, in addition to the continuing core group.
	DLW raised the need for contingency plans, should the shipment of
	equipment be delayed.

	Accommodation was recommended at Liversidge Apartments with overflow
	at University House, both located on campus and reasonably priced
	(\$357/wk for two-bed apartment, and \$42/day pp respectively,
	\$ $\approx $\pounds $\times 2.05$). Precise dates will be discussed
	at the next meeting, and firm bookings decided. \action{ALL}

\newpage
\item	 {\bf Packing for Shipment to the ANU:}

	Most of the electronics and data acquisition system had been packed
	up on 5/6 April by SJAH, RPW and RAH.

	The Suns ordered for use at ANU would be tested at DL prior to
	shipping in original packing. One exabyte drive presently at
	Birmingham and	one at DL are to go. The SparcPrinter is to be
	tested and packed along with toner cartridges, but the interface
	cards will be kept at DL for testing. \action{VP,SJAH}

	Packing for shipment will start on 19 April, with Union Air
	Transport Company. A note describing the general procedure had
	been circulated by DLW in the previous week (Ch/Doc/93/05). 
	DLW would be
	coordinating, and it was agreed that JSL and SJAH would also
	be present on the 19th. \action{DLW,JSL,SJAH}

	Computer manuals and exabyte tapes, hybrid detectors, cable runs
	and patch panels would be packed. Designated people would ensure that
	the target-area patch panels and long cable runs
	to the vault room (DLW/JK)
	and counting-area patch panels (JSL/WNC) were packed. JSL suggested
	that HV cables should be included for bias supplies.

	Extra connectors and a crimping tool for the blue superscreen
	cable should be ordered. \action{WNC,GJG}

	BRF planned to visit DL on 20 April to try and finalise DL minor
	details relevant to the packing. \action{BRF}

	The final day for packing was reported to be Friday 30 
	April. \action{ALL}

\item	 {\bf Documentation for ANU Running:}

	The document `Charissa at ANU' cited above includes helpful comments
	on documentation (Ch/Doc/93/04).

	The values of the various electronics modules being shipped to
	ANU were discussed for purposes of insurance. The
	value of the data acquisition system  required clarification.\\
	The latter information should be forwarded to SJAH. \action{RAH}

	The customs procedure -- in particular, whether part of the
	shipment can easily be brought back, independently --
	needs to be checked. \action{BRF}

\item	 {\bf Plans for Strasbourg:}

	NMC and DLW will be giving invited talks about Charissa at
	the Heavy Ion Workshop being held
	in Strasbourg on 5--7 May.

	Two representatives each from Surrey and York,
	one from Manchester (JSL!), and several from
	Birmingham will be attending.  It was hoped to build on earlier
	contacts with the ICARE group and others at Strasbourg, with a
	view to future collaboration.

	JSL agreed to investigate shipping the existing Charissa chamber
	to Strasbourg, as agreed at the previous Charissa meeting. \action{JSL}


\item	 {\bf Any Other Business:}


\begin{enumerate}

\item	 A letter had been received by the Universities, from DL, regarding
	money that had been brought forward to buy Charissa equipment. This
	would now be charged against the Grants, as previously agreed.

	It was agreed that at each university, the equipment line in the
	grant should have the Charissa component clearly separated.
	WNC agreed to ensure that the funds brought forward were debited
	against computing and not Charissa equipment at Surrey. \action{WNC}

\item	 BRF reported that Kui Zhao, who is Head of Nuclear Physics in
	Beijing and has recently spent time at Manchester, had approached
	the group. She was interested
	in discussing a joint agreement for exchanges.


\end{enumerate}

\item	 {\bf Date of Next Meetings:} \\

	Next Meeting: Thursday, 13 May 1993 in Birmingham,\\

	The date of the subsequent meeting was also decided.
	\footnote{Following Meeting: Thursday, 15 July 1993 in Oxford.
	(BRF, GT and SJAH will be in Canberra)}




\end{enumerate}


\mbox{}\\
W.N. Catford, Secretary.\\
April 26, 1993\\[1mm]
(released \today )

\end{document}















