\documentstyle[a4,psfig,12pt]{article}
%\setlength{\textwidth}{6.375 true in}
\setlength{\textwidth}{6.000 true in}
\setlength{\textheight}{655 pt}
%\pagestyle{empty}
\renewcommand{\thefootnote}{\fnsymbol{footnote}}
\newcommand{\cc }{$^{12}$C}
\newcommand{\oo }{$^{16}$O}
\newcommand{\mg }{$^{24}$Mg}
\newcommand{\be }{$^{8}$Be}
\newcommand{\si }{$^{28}$Si}
\newcommand{\neon }{$^{20}$Ne}
\newcommand{\he }{$^{4}$He}
\newcommand{\al }{$\alpha $}
\newcommand{\gam }{$\gamma $--ray}
\newcommand{\degree }{$^\circ $}
\newcommand{\action }[1]{\hfill \fbox{#1}}
\begin{document}

\setlength{\unitlength}{1cm}
\noindent
\begin{picture}(0,0)
\put(0,2.5){\makebox(0,0)[l]{CH/Meet/92/05}}   %% Reference number of document
\end{picture}

\noindent
\begin{minipage}[t]{10cm}
\fbox{
\parbox[t]{5cm}{
{\large {\bf Minutes}}\\[2mm]
Charissa Group Meeting
}}\\[7mm]
\makebox[3.5cm][l]{Meeting held on:} 7 October 1992\\[2mm]            % Date
\makebox[3.5cm][l]{Meeting held at:} Guildford (Surrey) \\[2mm]     % Place
\end{minipage}
\hfill \raisebox{-2.5cm}{
\psfig{figure=char-encap.ps,height=3cm}}\\[2mm]

\begin{center} \begin{tabular}{l@{~~}l} \hline
~\\								% Present
\makebox[2.5cm][l]{Present:} & \parbox[t]{12cm}{
BRF(Chair),WNC,GJG,CDJ,ACM,VP,WDMR,DLW
}\\
~\\								% Apologies
\makebox[2.5cm][l]{Apologies:} & \parbox[t]{12cm}{
NMC,RAC,RAH,JSL,GT
}\\
~\\								% Distribution
\makebox[2.5cm][l]{Distribution:} & \parbox[t]{12cm}{
Those present, plus NMC,RAC,RAH,JK, JSL, GT 
}\\
~\\ \hline
\end{tabular}
~\\[1cm]
%\addtolength{\headheight}{2.5cm}
{\large {\bf Minutes}} \\[1cm]
 \end{center}


\begin{enumerate}
%\addtocounter{enumi}{-1}

\item	{\bf Minutes of Meeting of 11 June 1992:} Accepted as a true record.
	
\item	{\bf Matters Arising:}\\
	All ACTIONS were briefly reviewed and found to be 
	adequately covered. In 
	particular, BRF had been approached by the NSC regarding the forward
	look, and was preparing a presentation for the meeting on 13 October.

\item	{\bf Update on NSC/SERC matters:}\\
	{\it Daresbury equipment:} The NSC has considered bids 
	for major equipment
	to be transferred from DL after shutdown. The major Charissa bids,
	for  electronics/data acquisition, scattering chamber and pumps
	were successful. Smaller items of equipment will be considered by a
	subgroup including the four project physicists, to meet initially on
	28 October.

	{\it Project Physicists:} It is expected that the NSC 
	will require  Project
	Physicists to report to  meetings at 6 
	monthly intervals, with summaries of expenditure and manpower usage
	to be submitted every three months. The four Projects funded by NSC
	are Charissa (B.R. Fulton), Eurogam (P.J. Nolan), ISOLDE (I.S. Grant)
	and Electromagnetic Probes (D. Branford).  Project
	physicists may contribute to NSC discussions (but not voting) as
	a representative of the collaboration.

	{\it New Board Structure for SERC:} As of September 1993, 
	nuclear structure 
	will be in the new `Physics, Space and Astronomy Board' and at best will
	have a subcommittee acting in an advisory role.
	\begin{center} 
	Outline of new SERC board structure\\[2mm]
	\begin{tabular}{llll}
	Council	& Board	& Committee	& Subcommittee \\ \hline
	SERC 	& Physics, Space 	& Plasma, Atomic, 	& ~ \\
	~	& ~~\& Astronomy		& ~~Classical Optics \&  & ~ \\
	~	& ~ 			& ~~Nuclear Physics
						& Theory (all fields) \\
	~	& ~			& ~ & Nuclear Physics? 	 \\
	~	& ~			& ~ & ~~~~(advisory?) \\
	~	& ~			& Particle Physics	& ~ \\
	~	& ~			& Astronomy		& ~ \\
	~	& ~			& Earth Observation	& ~ \\
	~	& Engineering		& ~ 			& ~ \\
	~	& ~~~~~~\& Technology	& ~ 			& ~ \\
	~	& Science \& Materials	& ~ 			& ~ \\
	\hline 
	\end{tabular} \end{center}
	{\it Vivitron:} A decision on the reaching of 25MV (without tubes) has
	been postponed until mid-December. Success will mean that Eurogam
	is sited at the Strasbourg Vivitron as originally planned.

	{\it Radioactive Nuclear Beams:} A total of \pounds 0.3M 
	had been approved
	by the NPB for the RNB test bed proposed for RAL. At least \pounds 1M
	is likely to be required to be found from existing projects.\\
	The meeting discussed the Charissa position regarding R\&D over the
	two years following the existing grants, i.e.\ Oct 94---Oct 96. Certain
	desirable development work was identified. The meeting agreed, however,
	that in the circumstances we would wish to demonstrate
	our support for the RNB development by concentrating on physics
	exploitation of the new array, and downplaying development (although
	a reduced expenditure on development would still be required with a
	view to using the array with RNB's). This position was adopted on the
	understanding that other Projects would show similar support.
	The chairman would report this position to the NSC. \action{BRF}

	{\it NSC membership:} DLW remains a member. Profs.\ Twin
	and Johnson have left, and Drs Nolan and Mackintosh have joined
	along with the new chairman Prof.\ Morrison. The Particle Physics
	member has also changed.

	{\it Next NSC Meeting:} Tuesday, 13 October, to consider the forward
	look, and BRF has been invited to attend.
	

\item	{\bf Report on Trip to the ANU:}\\
	WDMR reported in detail on his visit in September. The meeting agreed
	that much progress had been made with the detailed planning 
	of how to run experiments in Canberra.

	The visit resulted in the signing of an agreement in Canberra, 
	summarising important operational details. This document
	(Ch/Doc/92/07, ``Charissa at the Australian National University'')
	had been circulated within the collaboration and the ANU, and formed
	a basis for discussion at the meeting.

	A visit by a group member is scheduled for late December. 

	{\it Vacuum feedthroughs and detector mounts:} All
	feedthroughs, insulating panels and cabling to be supplied by us.
	Viton O--rings, insulated flanges (Macor ceramic, or teflon) required.
	This should be considered by the MEGHA subgroup; copies of the
	agreement with the relevant sections highlighted should be 
	distributed to MEGHA personnel. \action{MEGHA,WNC}

	{\it Cabling requirements:} this should also be considered by MEGHA,
	and the use of coaxial strip cables is very desirable. Around
	8---10 lengths of 50m may be required. \action{DLW}\\
	At the moment, only 32 cables are provided between chamber and
	control room.
	DL should be informed of our needs for runs of  coaxial
	cable. \action{BRF} 

	{\it Manning of experiments:} The ANU are keen that one RA and
	one Ph.D.\ student should stay in Canberra and collaborate with a
	group there for 6 months prior to our first experiment (i.e.\ April
	to Sep 1993). They believe this to be essential for efficient
	use of time, and satisfactory operation of the accelerator by
	Charissa experimenters. 

	The possibilities of funding a Charissa person to be based at
	the ANU should be discussed with Prof. G.D. Dracoulis 
	(Canberra). \action{BRF} 

	Running at the ANU is being planned for September 1993 and
	Easter 1994, with each anticipated to comprise 
	around 14 days of beamtime.
	Regarding the scheduling of manpower coverage in Australia,
	individual comments will be sought from each group member,
	and assimilated by BRF. \action{BRF}

	{\it SERC Student Support:} The means to support students in these
	circumstances must be established by the NSC.
	We should write to SERC to point out our
	needs within the new context wherein we are {\it obliged} to run 
	overseas. \action{BRF} \\

	{\it Beamline for the LINAC:} in accordance with Item 8(a) of the
	agreement, we will write to DL requesting a decision
	regarding the Charissa beamline by November 92 when
	Dr D.C. Weisser (Canberra) visits DL. \action{BRF}

	{\it Shipping of Equipment:} this is anticipated to follow immediately
	after Easter 1993 run at Lawrence Berkeley Laboratory.

	{\it Specified Responsibilities:} The ANU group have requested
	that the Charissa group should supply lists specifying (a) what
	we will achieve, and (b) what we are expecting from 
	them. \action{WDMR,BRF}

	{\it General Information About Running at the ANU:} 
	WDMR presented books and folders of information gathered during
	his visit. These include two booklets of photographs showing
	the target chamber and other experimental items, and engineering
	drawings of same. The originals will be kept in Birmingham.
	Indexes will be copied and put on the document 
	server (as CH/Doc/92/11). \\ \mbox{} \action{WNC}

\item	{\bf Progress on Scintillator Detectors:}\\
	NMC had sent a note summarising points relevant to Items 5, 8
	10 and 13. Comments on scintillators are included at Item 8.

\item	{\bf Progress on Silicon Detectors:}\\
	Two NSF shifts had been run on proposal 914 (detector tests) in 
	September. Data exist for two Q--Par Angus detectors of the sheet
	resistance type. Preliminary analysis at Birmingham 
	by M.\ Leddy is encouraging
	for position and energy resolution.
	Data for the NASA--style detector (orthogonal strips with integrated
	resistors) will be analysed at York by S.\ Fox. 

	The Hamamatsu detector is ready for testing. Beam time should be
	requested. A suitable time was anticipated to be immediately after
	the next tank opening. We should prepare for a run in the time 
	window 11--14 Nov, and get hardware ready to run at short
	notice, early November. \action{WNC}

	WDMR produced two preamplifier units to the new design (cf. Item 9)
	which could be used, and should be taken to Daresbury. \action{BRF}

	The Intertechnique detector had not arrived --- chase up. \action{BRF}

	The results of all these tests should be collated and written up
	as a Charissa document when complete. \action{WNC}

	The four strip detectors ordered by York from Micron had arrived.
	The 10 from Hamamatsu would be manufactured soon, as final checks
	on the PCB mask are now complete. The 2 Micron detectors ordered 
	by Birmingham (to make 16 new detectors in total) have arrived.
	Also, two detectors sent to Micron for repair to strip
	connections have returned.

\item	{\bf Progress on Gas Supply:}\\
	DLW reported that the subgroup on gas supply met after the last
	MEGHA meeting. Of the equipment ordered by York, 90\% had arrived 
	so far.
	Some minor differences in specifications are to be clarified at the
	next MEGHA meeting. \action{DLW}

	Preliminary plans are being made at York for
	construction of the pipework. A version of the control device is under
	test at York using a PC to control the PLU with a mimic system.


\item	{\bf Progress on Chamber and Detector Assemblies:}\\
	{\it Detector Flanges:} A submission from NMC noted 
	that a French manufacturer would be able
	to provide vacuum feedthroughs for 18-pin ribbon cables, secured by
	bolts with an O--ring. It is suggested that each of the 9 scintillator
	signals (signal line plus earth line) would come out on its own
	Sealectro push-on connector, to avoid an extra ribbon feedthrough.

	When the feedthroughs are ordered, spares for ANU should be obtained.

	{\it Strip Detectors:} it should be confirmed to the engineers at
	DL that strip detectors will be omitted from the present 
	design. \action{DLW} \\
	The concept of mounting strip detectors at a later date, within
	the same chamber, should be relayed in case it affects the present
	design work. \action{WDMR,DLW}

	{\it Target mechanism:} a Eurogam style device was suggested. This
	should be discussed at the next MEGHA meeting. \action{MEGHA}

	{\it Chamber:} the following necessary features were identified:
	\action{MEGHA} 
	\begin{itemize}
	\item collimator and anti-scatter aperture,
	\item target mechanism,
	\item gate valve to isolate chamber,
	\item pumping port,
	\item viewing port,
	\item anti-scatter baffles on side of cone where it splays out,
	\item cold shroud (possible),
	\item vacuum transfer for targets (possible).
	\end{itemize}

	{\it Prototype Module:} DLW reported that York would provide a
	correctly weighted model scintillator, for use in a prototype
	detector module to be constructed. The prototype would be used to
	test the practicalities of assembly and replacement.

\item	{\bf Progress Report on Electronics and Data Acquisition:}\\
	{\it Preamplifiers:} WDMR reported that two units had been modified
	to include the new design of preamp. One module
	contains preamps with 4.7 pF capacitors and hence
	the present standard gain of 10 mV/MeV (silicon).
	The other has 50 mV/MeV (silicon), or 5 mV/MeV (gas).
	These have the same circuit as previously, but now use 
	surface mounted technology.

	The new preamps cost 
	around \pounds 15 (replaceable component) per channel,
	plus bias resistors and capacitors, and are individually shielded.
	The previous design cost around \pounds 60 per unit including box 
	and rack share.

	{\it Bias Supplies:} The new method of compensation using computer
	control has been tested, and the new design should be ready in a few
	months.

	{\it Amplifiers:} final design estimated 
	to be ready in another three months.

	{\it Voltage-to-time conversion:} RAH is working on this, using
	the Lecroy chip, or possibly our own replacement together with a Silena
	sample-and-hold (peak detect) chip. The Lecroy MQT chip requires
	significant ancilliary electronics. The Silena chips can be purchased
	for \pounds 60 each. The options of gated integration or else
	analog integration (plus sample-and-hold) could be provided as
	alternatives with interchanging boards.

	{\it Tests using Lecroy TDC:} These have had to be cancelled due to
	DL requiring the 4300 TDC to be returned. The situation will be
	reviewed if the time conversion using the MQT chips is chosen.

	{\it Centralized Store of Equipment:} It was agreed that specialised
	electronics bought on the Charissa grant would be transferred to
	a central store at Oxford, after local inventory labelling at the
	purchasing institution. \action{WNC,DLW}

	We should investigate
	the manufacture of stickers small enough to attach to the front
	of CAMAC modules --- both a Charissa design,
	and individual institution labels similar to the old `Oxford Nuclear
	Physics' labels (which are metal, $8 \times 16$ mm$^2$). \action{WDMR}

	{\it Commitment of Funds:} The spend on preamps and bias supplies
	will be able to be estimated before the end of the year. The amplifiers
	will follow shortly after.


\item	{\bf Developments on Hybrid Detectors:}\\
	The note sent by NMC reported that R. Cunningham had completed the
	mods to the existing detectors: O--rings on the front windows, 
	new screws, revised connection to grid (EHT to go through preamp).
	At least three detectors will be ready for the \mg +\mg\ run, with
	a choice of 1.5 $\mu $m (as before) or 6 $\mu $m  
	windows (to accommodate 
	150 torr). New elbow-type gas connections, required for the same
	run, were in hand.

\item	{\bf Developments on Event Manager and GEC Emulation:}\\
	VP began by clarifying the `first order solution' identified for
	the data acquisition system in the previous Minutes (CH/Meet/92/04,
	Item 9). This has the exabyte in the control room area.
	A FERA link between target area and control room should be
	suitable, provided that it is optical.

	{\it CAMAC link:} Software has been received 
	from GPT to allow the 88K
	VME  processor to
	map the VME address space into its virtual address space.
	A modification to the CAMAC driver software now allows it to
	drive a HYTEC interface board and it does all CAMAC reads and writes.
	A LAM can be generated in the CAMAC crate, and this generates a demand
	message to the HYTEC interface, but the latter does not respond. This
	has been referred to HYTEC, but is not holding up the rest of the
	software tests.

	Data transfer rates between CAMAC and VME have been measured as
	1.4 Mbyte/sec in preliminary tests.

	The time required to install the link with the Charissa interface is
	estimated to be one month.

	{\it VME system:} A suitable VME crate may become available 
	at DL, but this is not certain.
	Two 160 Mbyte disks had been
	purchased for the VME system. These 3 1/2 inch disks mount on the
	back plane of VME cards. 
 	One disk is used for system software and programs. The other is left
	empty for spectra. A third disk (to be purchased) would be available
	as an online spare for either and would normally contain a 
	copy of the system software and programs.
	It must be decided whether this disk space is sufficient.

	{\it GEC emulator:} Regarding this unit that resides in VME, 
	the 88110 is not expected until June 1993,
	wheras the 88010 is available now. 

	{\it Peripherals:} Exabyte drives at DL are all committed to
	university grant requests, so two would need to be purchased for
	the new system. It is likely that two workstations would be
	needed, with their own disks for data replay.\\[1mm]

	From general discussion, the requirements for data acquisition
	stations were identified generally as:
	\begin{itemize}
	\item Main system: sort engine plus spares (first experiment at ANU)
	\item Oxford test bed: development, plus spares.
	\end{itemize}
	It was noted that the system should employ the minimum number of
	different components, to maximize interchangeability and spares.
	VP indicated that he was already adopting this criterion.

	It is necessary to identify precisely what is involved in the system
	to be used at the ANU. \action{VP,BRF}

	

\item	{\bf Update on Recent Analysis:}\\
	BRF summarised the results from Birmingham. AM has distributed
	a preliminary report on \mg + \mg , and plans are now being
	made for  another \mg +\mg\ run.

	The analysis by JP of the \oo --\be\ breakup of \mg , from the \mg\ 
	 beam experiment at DL  has reached the stage of
	extracting E$_{rel}$ spectra. The emphasis will now shift to the 
	LBL data with the \neon\ beam.

	WDMR reported that PS has almost finished analysis of the calibration
	data in the most recent chain state experiment.

	WNC reported that SUNsort has now been installed at Surrey.


\item	{\bf Discussion of Future Plans:}\\
	{\it Daresbury NSF:} We have 5 experiments, plus
	some development time (914) approved for the NSF:
		\begin{itemize}
		\item Proposal 874 (BRF) \mg +\mg\ 
		\item Proposal 900 (WDMR) \si\  chain state
		\item Proposal 903 (NMC) High resolution \mg $\rightarrow $
								\cc +\cc\ 
		\item Proposal 904 (DLW) \mg +\cc\  reaction mechanism
		\item Proposal 907 (BRF) \mg $\rightarrow $ \cc +\cc *
		\item Proposal 914 (WNC) Detector tests
		\end{itemize}
	but not all will be possible at Daresbury due to Eurogam commitments.

	Proposal 874: This will be run next. NMC's note reported that a
	cold trap has been designed to fit through the lid of the Charissa
	chamber to guard against carbon build-up.
	The hybrid detectors should be set up for the \mg +\mg\ experiment,
	ready to run at short notice, if Eurogam 
	has problems. \\ \mbox{} \action{BRF}

	Proposal 903: NMC's note reported that an offset target ladder had been
	constructed to increase the target--detector distance, thus maximizing
	the angular resolution (450 mm should be possible). A special means
	of collimation, using detector mounts, will be employed due to the
	altered target geometry.

	{\it LBL:} A run close to Easter 1993 is anticipated.

	{\it ANU Canberra:} It is anticipated that we will get approval for
	running the remaining NSF proposals at the ANU. The method for
	approval of other future ANU runs is still to be determined.


\item	{\bf Any Other Business:} \\
	WDMR reported that a CHARISSA account had been set up at the ANU
	for use by group members in connection with our work there.

	VP agreed to set up a `charissa' username at DL to allow ftp access
	to the Charissa document server. \action{VP}

	It was commented that e-mail to Oxford was getting bounced. This
	can be avoided by using name\%ph.v1@ox.ac.uk. WDMR can also be
	reached at \\ rae\%unix1.trinity@ox.ac.uk.

	New students joining us this year are:\\
	Steven Singer, Surrey, php3ss@surrey.ph\\
	Steve Chappell, York, \\
	Neil Curtis, Birmingham, nc@bham.ph.np

	The date of the Charissa 
	Physics Meeting was confirmed (4 November). The meeting
	will be planned around the Users' Meeting to be held that day, which
	WNC will be chairing.

\item	{\bf Date of Next Meeting:}
	11.30 am, {\em Wednesday} 25 November 1992 in York.


\end{enumerate}

\mbox{}\\
W.N. Catford, Secretary.\\
October 12, 1992\\[1mm]
(released \today )

\end{document}
